Sl No. |
Units |
Commissioned on |
1 | Raw Material Handling Plant | 29th December 2011 |
2 | Blast Furnace - 3 | 24th April 2012 |
3 | Turbo Blower - 4 | 20th April 2012 |
4 | Sinter Plant - 3 | 4th July 2013 |
5 | Steel Melt Shop (SMS) - 2 | |
| Caster - 1 | 27th January 2012 |
| Caster - 2 | 12th May 2012 |
| Caster - 3 | 28th November 2013 |
| Converter - 2 | 30th October 2013 |
| Converter - 1 | 28th March 2014 |
6 | Wire Rod Mill - 2 | 31st January 2014 |
7 | Special Bar Mill | 3rd April 2015 |
8 | Structural Mill | 30th April 2015 |
|
|